New York State Article 10 Process

The Bluestone Wind Farm project will be permitted pursuant to New York State’s Article 10 Siting Process prior to construction and operation.  As part of the Article 10 process, applicants are required to provide funds to be used to defray certain expenses incurred by municipal and local parties as they participate in the preapplication scoping process and in the proceeding before the Siting Board to consider the Article 10 Application based upon per megawatt fee formula.

Bluestone Wind, LLC has submitted its Article 10 application to the State of New York (Case #16-F-0559). 


Availability of Intervenor Funds and Deadline for Funding Requests (February 13, 2019) 

Intervenor funds in the amount of $124,000 have been made available by Bluestone Wind, LLC, as part of its Article 10 Application submitted on September 18, 2018. Funds are available to defray certain expenses to be incurred by eligible municipal and local intervenor parties in the application stage of this proceeding. Eligible municipal and local parties may request funds through close of business on February 13, 2019, by submitting their requests to the Examiners in this case, Administrative Law Judge Sean Mullany (sean.mullany@dps.ny.gov) of the Department of Public Service and Administrative Law Judge Daniel P. O’Connell (daniel.oconnell@dec.ny.gov) of the Department of Environmental Conservation. To access further details on intervenor funds made available and how to request them, please see the letter issued by the Siting Board on January 14, 2019. 

Information Forums and Public Statement Hearings (January 29, 2019)

The Siting Board also scheduled two public hearing sessions on the Application for January 29, 2019, from 2-3 p.m. and 6-7 p.m., at the Windsor Community House Meeting Room, 107 Main St., Windsor, NY 13865.  Click here to view the public meeting notice.

Article 10 Application Deemed Complete (December 27, 2018)

On December 27, 2018, the New York State Board on Electric Generation Siting and the Environment (“the Siting Board”) determined that the Article 10 Application filed by Bluestone Wind, LLC, complies with PSL §164.  Click here to access the Completeness Letter.

Article 10 Application Submitted (September 18, 2018)

Please see the application and other related documents below: 

For any questions regarding the application, please contact Alec Jarvis via e-mail (Alec.Jarvis@calpine.com) or phone (207-956-1169).

For more information on the Article 10 Process the links below.